All IS WELL!
Many people have asked if the weather affected the Construction site. A few small things but nothing that can’t be handled relatively easily.
As most of you know, the contractors only worked Monday of last week because of the weather. However, today everyone is back on track and many things are happening.
This morning 6 semi truck loads of steel were delivered. This is the first of three shipments of steel for the Super Structure of the building.

Last week the metal tile roof was delivered for the building. This morning the concrete contractor was on site laying out the footers for the building on paper. It will not be long that you will see him actually digging the footers.
The trucks are still running loads of crushed concrete and dumping them over the pipes in the underground retention area. 
Just to give you an idea of the magnitude of the retention. 425 truck loads of crushed concrete have already been dumped over the pipes and they are currently trucking in another 75 truck loads. They believe that once these trucks run then they can begin to fill the retention with dirt. Remember, the back parking lot will go over this retention area.
Speaking of parking lots, it looks like the front parking lot will be paved by this Sunday. The good news is that we will begin parking in that area for Sundays. The other news is that before long they will have to tear out the small parking area that is on your left as you enter and begin some construction in that area. However, the new parking area will have quite a few more spaces than the one they will tear out.
It is very exciting because things are really beginning to move forward now. However, please be patient because we will have to work around the construction for a while. It will all be worth it in the end.